Quality

Pre-shipment inspection in China: what to check

Plan a pre-shipment inspection with the right timing, checklist, sampling method, report and release decision.

Inspect when the batch can be judged and corrected

A pre-shipment inspection is usually scheduled when production is complete and most of the goods are packed, but before the final balance is released and the shipment leaves the factory. Inspecting too early can miss packing and quantity problems. Inspecting after dispatch removes the factory’s easiest opportunity to rework the batch.

Confirm the production status before the visit. The inspector should know the order quantity, quantity completed, quantity packed and where the goods are stored. If the full batch is not presented, the report must say so clearly.

Build the checklist from the order

The checklist should come from the approved specification, sample, purchase order and packaging files. It normally covers product identity, workmanship, dimensions, materials, colour, function, accessories, labels, manuals, unit packaging, cartons and shipping marks. Add tests that reflect real use and known risks.

Define which requirements are critical. A safety issue, wrong model or missing mandatory label should not be treated like a minor cosmetic mark. For machinery, the inspection may require a separate factory acceptance test with operating conditions, output and video evidence agreed in advance.

Choose a sampling method

Many consumer-goods inspections use an AQL sampling plan, but the level and defect limits must be agreed before the visit. A sample result estimates batch quality; it does not examine every unit. High-value, safety-critical or custom items may need a different approach, including more functional tests or a full count of selected characteristics.

The inspector should select samples from different cartons and locations instead of accepting pieces prepared by the factory. Record the sample size, defect classes and results so the buyer can understand the basis of the conclusion.

Read the evidence, not only pass or fail

A useful report identifies the factory, order, model, quantities and inspection date. It includes photographs of the goods, packaging, labels, tests and each discrepancy. Measurements should show the instrument and result when possible. The written conclusion should connect findings to the agreed checklist.

Review patterns as well as totals. Repeated defects in one component or carton group may point to a process problem even when the overall count is near the limit. Ask for clarification when photographs or descriptions do not support the conclusion.

Make and document the release decision

The buyer decides whether to accept, reject or require rework. If the batch fails, list the corrective actions, deadline and method of verification. A second inspection may be needed when rework affects many units or a critical requirement.

Do not release the final payment only because a report says “pass”. Confirm that quantities, documents and packing are complete and that any approved deviations are recorded. The inspection report is one part of the release file alongside the commercial documents and shipment plan.